Project Number: W5J9JE18C0003 |
Type: Vertical Construction and Horizontal Construction |
Location: Kabul, Afghanistan |
Project Owner's Name: USACE � Transatlantic Afghanistan District |
Project Completion Date: June 19, 2021 |
Contract Value: USD $ 20.8M |
Number of Buildings: 3 |
Total Built-up Area: 4,858 m2 x 3 Bldg |
Project Type: Design & Build - US Government Project |
Status: Completed |
The project is a Design-Build of a new Female Police Town (FPT) - Phase 1 for the Afghan National Police (ANP) in Kabul District, Kabul Province, Afghanistan. The project is defined as the design, material, labour, and equipment to construct three Family housing Buildings, six Guard Tower buildings, perimeter walls, parking and roads for Phase 1 area, utilities (water, electrical distribution, communications, sewage holding tanks/sewer lines) for the Phase 1 area. The scope also includes demolition and other infrastructure for a design population of approximately 300 Female Police Families.
To execute the project, MVL conducted a site survey, geotechnical investigation, UXO site clearing, and site improvement such as site grading, erosion control, roads, parking, sidewalks, force protection. It also includes utilities such as water distribution system, sanitary collection system, overhead/underground MV primary and secondary distribution system, site communication system.